Argogroup Exact Ltd. has carried out the construction and renovation works of M-tel Trade Centers all around the country from August until December 2010
Rough Construction of Administration building with shops and underground garage in Lozenets District,Cherni vrah blv., Sofia
Developed built up аrea of 1300 sq. m
Construction period:24.08.2012 - 31.12.2013
Supermarket, Veliko Tarnovo. Developed built up area of 1800 sq. m
Construction period: 02 March - 16 July 2012
Supermarket, Vazrajdane District, Sofia
Developed built up area of 1975 sq. m
Construction period: 28.08.2013 – 8.01.2014
Hypermarket,Smolyan
Developed build up area of 3000 sq.m
Construction terms: 06.06.2011 - 10.10.2011
Supermarket, Sliven
Developed built up area: 1700 sq. m.
Construction period: 19 December - 11 April 2012
Supermarket, Shumen
Developed built up area: 1800 sq. m.
Construction period: 24 August - 20 December
Supermarket, Ruse
Developed built up area: 1900 sq. m.
Construction period: 14 February - 14 July 2012
Supermarket, Plovdiv, Peshtersko Shose Blvd.
Developed build up area: 1624 sq. m
Construction period: 05 August – 20 December 2010
Supermarket, Plovdiv, Makedonia Blvd.
Developed build up area: 1824 sq. m
Construction period: 04 October - 31 December 2010