Residential Building with shops,underground garages and room for substation
Completion stage Act 16
New developed area: 35 000 sq. m
Implementation period: from 6.06.2015 to 20.10.2017
White Church – Simeonovo Residential Complex consists of nine three-floor houses, each one supplied with a garret floor, a basement, a garage, and a parking place. Each house has total build-up area of 270 m2, a self-contained planted courtyard with total area of 100 m2 up to 250 m2 , and local gas heating system. Panoramic view to Vitosha Mountain and Sofia. Dead line: March 2009
White Church - Kambanite Residential Complex, Sofia, total area: 2 500 sq.m. Construction terms: June – December 2008. Situated in the foot of Vitosha Mountain, White Church – Kambanite is a gated residential complex, consisting of twelve houses, each one provided with a parking place and a self-contained planted courtyard, an access control system. We offer calm and comfortable houses combining the advantages of the surrounding environment with fast and easy access to the center of Sofia. Each house having total build-up area of 270 sq. m. consists of a basement, two floors, and a garret floor. The complex is going to be build-up in accordance with all modern standards and with concern for the natural environment. A support agreement, which includes maintenance of the green areas, 24-hour human and machine guarding, a video security and access control system and etc., is attached to the sale contract.
Seasonal residential building in St. Vlas, Nesebar
Total area: 4500 sq.m
Construction terms: October 2005 - July 2006
Rough construction of Residential building plot,Krasno Selo - Shooting "- Sofia
Developed built up аrea: 1447.05 sq.m
Construction period: 15.01.2014 - 30.06.2014
Residential Building with shops and underground garages, Ivan Vazov District - South Park, Sofia
Developed built up area: 7 000 sq. m
Construction period: 01 May 2010 - 12 February 2012
Residential building with shops, offices and underground garage in Reduta District, Sofia
Developed built up area: 3000 sq.m
Construction period: 23 April 2012 - 15 December 2012
Residential building with shops, offices, studious and underground garages, Ivan Vazov district, Sofia
Developed built up area: 12 500 sq. m
Construction period of structural works: 22 February 2012
Construction period of overall facade and roof: 10 January 2013
Seasonal residential building in Ravda, near the Black sea
Total area: 1300 sq.m
Construction terms:November 2004 - May 2005
Family Recreation Complex Pamporovo
Total area: 4500 sq.m
Construction terms: April- December 2005