Supermarket, Samokov
New developed area: 31980 sq. m
Implementation period: from 21.02.2017 to 03.07.2017
Supermarket, Sofia, Mladost
New developed area: 2178 sq.m
Implementation period: from 01.03.2016 to 13.08.2016
Warehouse depot Razgrad propane-butane
Implementation period: from 15.11.2016 to 24.02.2017
Rehabilitation on site flooring on gas station Shell Enevo South
Area: 5149 m2
Implementation period: 7.09.2016 - 7.10.2016
Hypermarket, Sofia, Tsar Boris III
New developed area: 6482 sq. m
Implementation period: from 5.05.2016 г. to 18.01.2017
Buildings and equipments of FOS Novo Selo Training range in Bulgaria
Completion stage - design&build
Implementation period for first stage: from 15.01.2016 to 07.07.2017
Implementation period for second stage: from 08.04.2016 to 31.07.2017
Implementation period for third stage: from 01.09.2017 to 31.07.2018
Auto showroom, offices and warehouse, Gorny Bogrov
Completion stage Act 16
New developed area: 3175 sq. m
Implementation period: from 11.05.2016 to 31.08.2017
Residential Building with underground garage, Sofia, Krustova Vada
New developed area: 2300 sq. m
Implementation period: from 18.04.2016 to 15.06.2017
Office building with shops and underground parking on Cherni Vrah Blvd., Sofia
Developed built up area of 10 000 sq.m.
Deadline for construction period: 22 September 2012
Office building with shops and underground parking on Cherni Vrah Blvd., Sofia
Developed built up area of 10 000 sq.m.
Deadline for construction period: 22 September 2012