Administrative building with shops and underground garages "Darik Radio", Sofia

Completion stage Act 14

New developed area: 4 303 sq. m

Implementation period: from 07.03.2017 to 02.12.2017

Reconstruction of  cinema "Lumiere

Implementation period: from 31.01.2017 to 08.03.2017

 

Supermarket, Samokov

New developed area: 31980 sq. m

Implementation period: from 21.02.2017 to 03.07.2017

 

Supermarket, Sofia, Mladost

New developed area: 2178 sq.m

Implementation period: from 01.03.2016 to 13.08.2016 

Warehouse depot Razgrad propane-butane

Implementation period: from 15.11.2016 to 24.02.2017 

Rehabilitation on site flooring on gas station Shell Enevo South

Area: 5149 m2

Implementation period: 7.09.2016 - 7.10.2016

 

 

Hypermarket, Sofia, Tsar Boris III

New developed area: 6482 sq. m

 Implementation period: from 5.05.2016 г. to 18.01.2017

 

 

Auto showroom, offices and warehouse, Gorny Bogrov

Completion stage Act 16

New developed area: 3175 sq. m

Implementation period: from 11.05.2016 to 31.08.2017

 

Residential Building with underground garage, Sofia, Krustova Vada

New developed area: 2300 sq. m

Implementation period: from 18.04.2016 to 15.06.2017 

Office building with shops and underground parking on Cherni Vrah Blvd., Sofia

Developed built up area of 10 000 sq.m.

 Deadline for construction period: 22 September 2012